Tag: Zakhem International Construction Ltd

  • Zakhem International Accused of Sh537 Million Fraud, Faces Liquidation

    Zakhem International Accused of Sh537 Million Fraud, Faces Liquidation

    Nairobi — Lebanese construction giant Zakhem International is staring down a potentially devastating liquidation after allegedly failing to pay a Sh537 million debt to a Kenyan subcontractor, Azicon Kenya Limited, despite having received full compensation from the Kenya Pipeline Company (KPC).

    Azicon, which provided electrical, instrumentation, and telecommunication installation services for the Mombasa-Nairobi pipeline upgrade, claims it completed the work in 2018 and received formal certification for payment in March 2019. However, more than six years later, the balance remains unpaid .

    Zakhem had subcontracted Azicon as part of the Sh48 billion pipeline replacement project commissioned by KPC in 2014.

    While Zakhem received full payment from KPC, it only transferred Sh840 million to Azicon, leaving a balance of Sh537.3 million (approximately $4.16 million), which the Kenyan firm says has never been disputed but remains unpaid .

    In a damning ruling, High Court judge Lawrence Mugambi dismissed Zakhem’s attempt to block insolvency proceedings, declaring that the company had failed to comply with a statutory 21-day payment demand served in January 2025.

    “It is, therefore, [Azicon’s] reasonable conclusion that, by failing to comply… Zakhem International is unable to pay its debt and is consequently liable to be liquidated,” Justice Mugambi stated .

    This isn’t the first time Zakhem has faced legal trouble with subcontractors.

    In a separate case last year, another firm, Multiple ICD (Kenya) Ltd, sued for Sh670 million, even obtaining a court order to freeze KPC accounts—an order later lifted when it emerged that KPC no longer held any money for Zakhem .

    Azicon’s Managing Director, David Kibet Tonui, had previously obtained a court order in 2020 compelling Zakhem to pay the outstanding amount, but enforcement has been frustrated by what the firm describes as deliberate non-compliance .

    Court affidavits from both Zakhem and KPC confirm that the Lebanese firm was paid in full and later withdrew its own lawsuit against KPC—evidence, the court found, that the money was indeed received. This leaves Azicon legally cleared to pursue liquidation and asset auction to recover the debt .

    The case lays bare the vulnerability of local firms in high-stakes infrastructure projects often dominated by foreign contractors.

    As the court prepares for final determinations, the fallout could mark a turning point in how Kenya handles foreign firms accused of financial malpractice against local partners.

  • Too Broke: Lebanese Firm Zakhem Faces Liquidation Over Sh460 Million Debt

    Too Broke: Lebanese Firm Zakhem Faces Liquidation Over Sh460 Million Debt

    A Kenyan firm has initiated insolvency proceedings against Lebanese construction company Zakhem International Construction Ltd over an unpaid debt of approximately Sh460 million ($3.56 million), potentially forcing the once-prominent contractor into liquidation.

    Azicon Kenya Ltd filed the petition in the Nairobi High Court, claiming that Zakhem International has failed to settle the outstanding amount since 2020.

    The debt stems from subcontracted electrical, instrumentation, and telecommunications installation work on the Sh48 billion Nairobi-Mombasa pipeline replacement project completed in 2019.

    “The debtor has never disputed the excellent work done but failed to meet its part of the subcontract,” said Azicon Kenya Managing Director David Kibet Tonui in court filings.

    According to court documents, Azicon Kenya was awarded a subcontract worth $10.14 million inclusive of VAT, but Zakhem International allegedly paid only $6.51 million before refusing to settle the remaining balance.

    Despite obtaining a court order in September 2020 compelling payment, Azicon claims Zakhem International has avoided its financial obligations.

    The company served Zakhem with an insolvency statutory demand on January 14, 2025, which went unaddressed for the required 21-day period.

    Azicon’s legal representative, Collins Taliti, accused Zakhem of deliberately misleading the court by claiming it was still awaiting payment from Kenya Pipeline Company (KPC), which commissioned the original project.

    “The debtor is deliberately and blatantly telling lies,” stated Taliti, citing affidavits proving KPC has already paid Zakhem International all amounts related to the project.

    This includes an affidavit dated November 8, 2024, from Ibrahim Zakhem confirming that KPC was not holding any funds on its behalf.

    This isn’t the first financial dispute involving Zakhem International’s work on the pipeline project.

    Last year, another subcontractor, Multiple ICD (Kenya) Ltd, pursued a debt of Sh670 million from the Lebanese firm.

    The case highlights growing concerns about Zakhem International’s financial stability, with Azicon alleging the company is “busy scheming and deliberately avoiding to pay by incorporating new companies to hide therein all the monies and assets belonging to Zakhem International Construction Limited in order to defeat justice.”

    If the court rules in favor of Azicon Kenya, Zakhem International could face liquidation, marking a dramatic downfall for the international construction company that once secured major infrastructure contracts in Kenya.​​​​​​​​​​​​​​​​